SR Peach
57 MW generation in Peach, GA · In queue since December 2024 · Proposed COD December 2029
57 MW
Capacity
1
Components
Solar
1y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
State
GA
County
Peach
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Ft. Valley #1 - Ft. Valley #2 115 kV line
Data Source
LBNL
Construction on new BESS gets under way by Georgia Power
Georgia Power, the largest electric subsidiary of the Southern Company, announced Monday that construction has started on its new 200-megawatt (MW) battery...
Construction on new BESS gets under way by Georgia Power
Georgia Power, the largest electric subsidiary of the Southern Company, announced Monday that construction has started on its new 200-megawatt (MW) battery...
Construction on new BESS gets under way by Georgia Power
Georgia Power, the largest electric subsidiary of the Southern Company, announced Monday that construction has started on its new 200-megawatt (MW) battery...
Construction on new BESS gets under way by Georgia Power
Georgia Power, the largest electric subsidiary of the Southern Company, announced Monday that construction has started on its new 200-megawatt (MW) battery...
Last updated 2026-03-26