Scarboro Solar
BetaActiveSolarBatteryGTCLBNL
125 MW hybrid in Miller, GA · In queue since December 2024 · Proposed COD February 2031
125 MW
Capacity
1
Components
Solar
1y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
6y 2m
In Study38%
Queue EntryDec 17, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-02-28
Project Details
State
GA
County
Miller
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Grove Church 115 kV Substation
Data Source
LBNL