Rebecca Solar
BetaActiveSolarGTCLBNL
120 MW generation in Turner, GA · In queue since December 2024 · Proposed COD December 2028
120 MW
Capacity
1
Components
Solar
1y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntryDec 11, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
GA
County
Turner
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
North Tifton - Pitts 230 kV line
Data Source
LBNL
No news available for this project.