Flint River 780 MW Unit
BetaActiveGasGTCLBNL
780 MW generation in Mitchell, GA · In queue since October 2024 · Proposed COD August 2029
780 MW
Capacity
1
Components
Gas
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 10m
Impact Study25%
Queue EntryOct 9, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-08-01
Project Details
State
GA
County
Mitchell
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Raccoon Creek Substation
Data Source
LBNL