SR Grady
BetaActiveSolarGTCLBNL
150 MW generation in Grady, GA · In queue since August 2024 · Proposed COD December 2028
150 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
Impact Study25%
Queue EntryAug 31, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-15
Project Details
State
GA
County
Grady
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
South Bainbridge _x0013_ Thomasville 230 kV TL
Data Source
LBNL
No news available for this project.