Altamaha Green Energy
BetaActiveOtherGTCLBNL
70 MW generation in Wayne, GA · In queue since August 2024 · Proposed COD March 2028
70 MW
Capacity
1
Components
Other
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 7m
Impact Study25%
Queue EntryAug 20, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
GA
County
Wayne
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Jessup _x0013_ Ludowici Primary 115 kV TL
Data Source
LBNL
No news available for this project.