Smarr CC — Project Summary

Queue ID
GTC-GI-193
Capacity
2000 MW
Technology
Gas
Status
active
Location
Monroe, GA
Region
Southeast
Developer
IA Status
In Progress (unknown study)

Smarr CC

BetaActiveGasGTCLBNL

2,000 MW generation in Monroe, GA · In queue since August 2024 · Proposed COD March 2028

2,000 MW

Capacity

1

Components

Gas

1y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 7m

In Study38%
Queue EntryAug 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-31

Project Details

State

GA

County

Monroe

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Big Smarr 500 kV substation (TBD)