Smarr CC
2,000 MW generation in Monroe, GA · In queue since August 2024 · Proposed COD March 2028
2,000 MW
Capacity
1
Components
Gas
1y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
State
GA
County
Monroe
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Big Smarr 500 kV substation (TBD)
Data Source
LBNL
Oglethorpe Power Picks Kiewit Unit as EPC for $2.5B Gas-Fired Georgia Power Plant
The Industral Co. will start construction in spring on 1.425-GW combined‑cycle plant in Monroe County to meet rising electricity demand...
Oglethorpe Power Picks Kiewit Unit as EPC for $2.5B Gas-Fired Georgia Power Plant
The Industral Co. will start construction in spring on 1.425-GW combined‑cycle plant in Monroe County to meet rising electricity demand...
Oglethorpe Power Picks Kiewit Unit as EPC for $2.5B Gas-Fired Georgia Power Plant
The Industral Co. will start construction in spring on 1.425-GW combined‑cycle plant in Monroe County to meet rising electricity demand...
Oglethorpe Power Picks Kiewit Unit as EPC for $2.5B Gas-Fired Georgia Power Plant
The Industral Co. will start construction in spring on 1.425-GW combined‑cycle plant in Monroe County to meet rising electricity demand...
Last updated 2026-03-26