Peanut Solar — Project Summary

Queue ID
GTC-GI-191
Capacity
210 MW
Technology
Solar
Status
active
Location
Washington, GA
Region
Southeast
Developer
IA Status
In Progress (unknown study)

Peanut Solar

BetaActiveSolarGTCLBNL

210 MW generation in Washington, GA · In queue since May 2024 · Proposed COD September 2028

210 MW

Capacity

1

Components

Solar

1y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntryMay 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-29

Project Details

State

GA

County

Washington

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Wadley Primary _x0013_ Warthen 500 kV TL line

Data Source

LBNL