Peanut Solar
210 MW generation in Washington, GA · In queue since May 2024 · Proposed COD September 2028
210 MW
Capacity
1
Components
Solar
1y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-29
State
GA
County
Washington
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Wadley Primary _x0013_ Warthen 500 kV TL line
Data Source
LBNL
Trump administration decision leaves Georgia farmers and rural businesses in limbo
WABE climate reporter Emily Jones joined "All Things Considered" to talk about the Trump administration's freeze on funding of the Rural...
Jimmy Carter, champion of solar energy
Jimmy Carter, a peanut farmer from Plains, Georgia, became the first American president to champion solar energy as a key to energy independence.
Last updated 2026-03-26