Spain Energy Center
BetaActiveSolarBatteryGTCLBNL
141 MW hybrid in Brooks, GA · In queue since January 2024 · Proposed COD December 2028
141 MW
Capacity
1
Components
Solar
2y 2m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 11m
Impact Study25%
Queue EntryJan 9, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-13
Project Details
State
GA
County
Brooks
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Spain 230 kV Substation
Data Source
LBNL
No news available for this project.