TOCE GA Solar 4
BetaActiveSolarGTCLBNL
100 MW generation in Jefferson, GA · In queue since January 2024 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
2y 2m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Impact Study25%
Queue EntryJan 8, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
GA
County
Jefferson
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Wadley _x0013_ Waynesboro TL line tap
Data Source
LBNL
No news available for this project.