TOCE GA Solar 2 — Project Summary

Queue ID
GTC-GI-188
Capacity
350 MW
Technology
Solar
Status
active
Location
Bartow, GA
Region
Southeast
Developer
IA Status
In Progress (unknown study)

TOCE GA Solar 2

BetaActiveSolarGTCLBNL

350 MW generation in Bartow, GA · In queue since January 2024 · Proposed COD July 2027

350 MW

Capacity

1

Components

Solar

2y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 6m

In Study38%
Queue EntryJan 8, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

Project Details

State

GA

County

Bartow

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Bowen _x0013_ Judy Mountain 230 kV line tap

Data Source

LBNL