TOCE GA Solar 2
BetaActiveSolarGTCLBNL
350 MW generation in Bartow, GA · In queue since January 2024 · Proposed COD July 2027
350 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 6m
In Study38%
Queue EntryJan 8, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
GA
County
Bartow
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Bowen _x0013_ Judy Mountain 230 kV line tap
Data Source
LBNL
No news available for this project.