Pecan Energy Storage — Project Summary

Queue ID
GTC-GI-187
Capacity
207.6 MW
Technology
Solar+Battery
Status
active
Location
Mitchell, GA
Region
Southeast
Developer
IA Status
System Impact Study

Pecan Energy Storage

BetaActiveSolarBatteryGTCLBNL

207.6 MW hybrid in Mitchell, GA · In queue since October 2023 · Proposed COD April 2029

207.6 MW

Capacity

1

Components

Solar

2y 5m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 6m

Impact Study25%
Queue EntryOct 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-30

Project Details

State

GA

County

Mitchell

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Raccoon Creek 230 kV SS

Data Source

LBNL