Pecan Energy Storage
BetaActiveSolarBatteryGTCLBNL
207.6 MW hybrid in Mitchell, GA · In queue since October 2023 · Proposed COD April 2029
207.6 MW
Capacity
1
Components
Solar
2y 5m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 6m
Impact Study25%
Queue EntryOct 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-30
Project Details
State
GA
County
Mitchell
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Raccoon Creek 230 kV SS
Data Source
LBNL
No news available for this project.