Beaver Creek Solar
BetaActiveSolarBatteryGTCLBNL
183 MW hybrid in Baldwin, GA · In queue since September 2023 · Proposed COD April 2027
183 MW
Capacity
1
Components
Solar
2y 6m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Impact Study25%
Queue EntrySep 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
GA
County
Baldwin
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Gordon - Milledgeville (White) 115 kV TL
Data Source
LBNL
No news available for this project.