SR Rochelle II Solar
BetaActiveSolarGTCLBNL
90 MW generation in Wilcox, GA · In queue since September 2023 · Proposed COD November 2026
90 MW
Capacity
1
Components
Solar
2y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 2m
Construction75%
Queue EntrySep 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-11-01
Project Details
State
GA
County
Wilcox
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Fitzgerald - Pitts 115 kV TL
Data Source
LBNL
No news available for this project.