Pelham Solar
BetaActiveSolarGTCLBNL
120 MW generation in Charlton, GA · In queue since September 2023 · Proposed COD November 2025
120 MW
Capacity
1
Components
Solar
2y 6m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 2m
Schedule
4 months past proposed COD
Impact Study25%
Queue EntrySep 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-30
Project Details
State
GA
County
Charlton
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Folkston - St. George 115 kV TL
Data Source
LBNL