Hammond Solar — Project Summary

Queue ID
GTC-GI-181
Capacity
225 MW
Technology
Solar
Status
active
Location
Floyd, GA
Region
Southeast
Developer
IA Status
System Impact Study

Hammond Solar

BetaActiveSolarGTCLBNL

225 MW generation in Floyd, GA · In queue since September 2023 · Proposed COD November 2025

225 MW

Capacity

1

Components

Solar

2y 6m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 2m

Schedule

4 months past proposed COD

Impact Study25%
Queue EntrySep 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-30

Project Details

State

GA

County

Floyd

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Hammond - Anniston 230 kV TL

Data Source

LBNL

No news available for this project.