Pepper Hammock 200 MW
BetaActiveSolarGTCLBNL
200 MW generation in Glynn, GA · In queue since August 2023 · Proposed COD August 2026
200 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3 years
Facilities Study50%
Queue EntryAug 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-08-30
Project Details
State
GA
County
Glynn
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Thalmann - Offerman 230 kV TL
Data Source
LBNL