TOCE GA 1 Solar
BetaActiveSolarGTCLBNL
125 MW generation in Burke, GA · In queue since August 2023 · Proposed COD September 2026
125 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 1m
Impact Study25%
Queue EntryAug 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
GA
County
Burke
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Greens Cut - Greens Cut Junction 115 kV Tap
Data Source
LBNL