SR Mendes — Project Summary

Queue ID
GTC-GI-176
Capacity
60 MW
Technology
Solar
Status
active
Location
Tattnall, GA
Region
Southeast
Developer
IA Status
Facility Study

SR Mendes

BetaActiveSolarGTCLBNL

60 MW generation in Tattnall, GA · In queue since July 2023 · Proposed COD December 2026

60 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 5m

Facilities Study50%
Queue EntryJul 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

GA

County

Tattnall

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Claxton-Ludowici Primary 115 kV

Data Source

LBNL

No news available for this project.