Live Oak Solar — Project Summary

Queue ID
GTC-GI-175
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Laurens, GA
Region
Southeast
Developer
IA Status
System Impact Study

Live Oak Solar

BetaActiveSolarBatteryGTCLBNL

200 MW hybrid in Laurens, GA · In queue since May 2023 · Proposed COD October 2026

200 MW

Capacity

1

Components

Solar

2y 10m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 5m

Impact Study25%
Queue EntryMay 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-05

Project Details

State

GA

County

Laurens

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

230 kV Bus at North Dublin 230 kV SS

Data Source

LBNL

No news available for this project.