Live Oak Solar
BetaActiveSolarBatteryGTCLBNL
200 MW hybrid in Laurens, GA · In queue since May 2023 · Proposed COD October 2026
200 MW
Capacity
1
Components
Solar
2y 10m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 5m
Impact Study25%
Queue EntryMay 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-05
Project Details
State
GA
County
Laurens
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
230 kV Bus at North Dublin 230 kV SS
Data Source
LBNL