Canoochee River Solar — Project Summary

Queue ID
GTC-GI-174
Capacity
152 MW
Technology
Solar+Battery
Status
active
Location
Emanuel, GA
Region
Southeast
Developer
IA Status
Facility Study

Canoochee River Solar

BetaActiveSolarBatteryGTCLBNL

152 MW hybrid in Emanuel, GA · In queue since May 2023 · Proposed COD November 2026

152 MW

Capacity

1

Components

Solar

2y 10m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

Facilities Study50%
Queue EntryMay 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-01

Project Details

State

GA

County

Emanuel

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Live Oak - Wadley Primary 115 kV TL

Data Source

LBNL

No news available for this project.