SR Norwood Solar
BetaActiveSolarGTCLBNL
107 MW generation in Warren, GA · In queue since May 2023 · Proposed COD June 2026
107 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 1m
Facilities Study50%
Queue EntryMay 2, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
GA
County
Warren
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Ray Place Road-Warrenton Primary 115 kV TL
Data Source
LBNL
No news available for this project.