Red Dirt Solar
BetaActiveSolarBatteryGTCLBNL
153 MW hybrid in Talbot, GA · In queue since April 2023 · Proposed COD September 2026
153 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 5m
Facilities Study50%
Queue EntryApr 6, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
GA
County
Talbot
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Patsiliga Creek - Talbot County #1 230 kV
Data Source
LBNL