Brenneman Solar
BetaActiveSolarGTCLBNL
150 MW generation in Macon, GA · In queue since November 2022 · Proposed COD November 2024
150 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2 years
Schedule
16 months past proposed COD
Facilities Study50%
Queue EntryNov 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-30
Project Details
State
GA
County
Macon
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
North Americus _x0013_ Perry 115 kV TL
Data Source
LBNL
No news available for this project.