Brenneman Solar — Project Summary

Queue ID
GTC-GI-169
Capacity
150 MW
Technology
Solar
Status
active
Location
Macon, GA
Region
Southeast
Developer
IA Status
Facility Study

Brenneman Solar

BetaActiveSolarGTCLBNL

150 MW generation in Macon, GA · In queue since November 2022 · Proposed COD November 2024

150 MW

Capacity

1

Components

Solar

3y 4m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2 years

Schedule

16 months past proposed COD

Facilities Study50%
Queue EntryNov 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-11-30

Project Details

State

GA

County

Macon

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

North Americus _x0013_ Perry 115 kV TL

Data Source

LBNL