Pepper Hammock 500 Solar
BetaActiveSolarGTCLBNL
500 MW generation in Glynn, GA · In queue since July 2022 · Proposed COD August 2024
500 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 1m
Schedule
19 months past proposed COD
Facilities Study50%
Queue EntryJul 6, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-08-30
Project Details
State
GA
County
Glynn
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Hatch - Thalmann 500 kV TL
Data Source
LBNL