Pepper Hammock Solar — Project Summary

Queue ID
GTC-GI-166
Capacity
200 MW
Technology
Solar
Status
active
Location
Glynn, GA
Region
Southeast
Developer
IA Status
Facility Study

Pepper Hammock Solar

BetaActiveSolarGTCLBNL

200 MW generation in Glynn, GA · In queue since June 2022 · Proposed COD August 2024

200 MW

Capacity

1

Components

Solar

3y 9m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 2m

Schedule

19 months past proposed COD

Facilities Study50%
Queue EntryJun 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-08-30

Project Details

State

GA

County

Glynn

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Offerman 230 kV -Thalmann 230 kV TL

Data Source

LBNL