Pepper Hammock Solar
BetaActiveSolarGTCLBNL
200 MW generation in Glynn, GA · In queue since June 2022 · Proposed COD August 2024
200 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 2m
Schedule
19 months past proposed COD
Facilities Study50%
Queue EntryJun 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-08-30
Project Details
State
GA
County
Glynn
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Offerman 230 kV -Thalmann 230 kV TL
Data Source
LBNL
No news available for this project.