Little Cedar Solar — Project Summary

Queue ID
GTC-GI-165
Capacity
150 MW
Technology
Solar
Status
active
Location
Baldwin, GA
Region
Southeast
Developer
IA Status
Facility Study

Little Cedar Solar

BetaActiveSolarGTCLBNL

150 MW generation in Baldwin, GA · In queue since June 2022 · Proposed COD October 2025

150 MW

Capacity

1

Components

Solar

3y 9m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 4m

Schedule

6 months past proposed COD

Facilities Study50%
Queue EntryJun 20, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-01

Project Details

State

GA

County

Baldwin

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

N. Milledgeville to Tap 230 kV TL

Data Source

LBNL

No news available for this project.