Crawford Solar
BetaActiveSolarBatteryGTCLBNL
160 MW hybrid in Crawford, GA · In queue since June 2022 · Proposed COD December 2025
160 MW
Capacity
1
Components
Solar
3y 9m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 6m
Schedule
3 months past proposed COD
Impact Study25%
Queue EntryJun 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
GA
County
Crawford
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Dorsett(GTC)-Thomaston 230 kV TL
Data Source
LBNL