Crawford Solar — Project Summary

Queue ID
GTC-GI-164
Capacity
160 MW
Technology
Solar+Battery
Status
active
Location
Crawford, GA
Region
Southeast
Developer
IA Status
System Impact Study

Crawford Solar

BetaActiveSolarBatteryGTCLBNL

160 MW hybrid in Crawford, GA · In queue since June 2022 · Proposed COD December 2025

160 MW

Capacity

1

Components

Solar

3y 9m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

3 months past proposed COD

Impact Study25%
Queue EntryJun 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

GA

County

Crawford

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Dorsett(GTC)-Thomaston 230 kV TL

Data Source

LBNL

No news available for this project.