Two Rivers Solar — Project Summary

Queue ID
GTC-GI-162
Capacity
102 MW
Technology
Solar+Battery
Status
active
Location
Camden, GA
Region
Southeast
Developer
IA Status
Facility Study

Two Rivers Solar

BetaActiveSolarBatteryGTCLBNL

102 MW hybrid in Camden, GA · In queue since March 2022 · Proposed COD December 2024

102 MW

Capacity

1

Components

Solar

4 years

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 9m

Schedule

15 months past proposed COD

Facilities Study50%
Queue EntryMar 16, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-20

Project Details

State

GA

County

Camden

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Browntown 115 kV Substation

Data Source

LBNL