Two Rivers Solar
102 MW hybrid in Camden, GA · In queue since March 2022 · Proposed COD December 2024
102 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 9m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-20
State
GA
County
Camden
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Browntown 115 kV Substation
Data Source
LBNL
Arizona solar policy hinges on this year’s Salt River Project elections
The vote, which takes place between March 11 and April 7, will determine the leadership of the Salt River Project and could have profound...
Arizona solar policy hinges on this year’s Salt River Project elections
The vote, which takes place between March 11 and April 7, will determine the leadership of the Salt River Project and could have profound...
Arizona solar policy hinges on this year’s Salt River Project elections
The vote, which takes place between March 11 and April 7, will determine the leadership of the Salt River Project and could have profound...
Arizona solar policy hinges on this year’s Salt River Project elections
The vote, which takes place between March 11 and April 7, will determine the leadership of the Salt River Project and could have profound...
Last updated 2026-03-26