Meriwether Panther Solar — Project Summary

Queue ID
GTC-GI-161
Capacity
125 MW
Technology
Solar+Battery
Status
active
Location
Meriwether, GA
Region
Southeast
Developer
IA Status
System Impact Study

Meriwether Panther Solar

BetaActiveSolarBatteryGTCLBNL

125 MW hybrid in Meriwether, GA · In queue since January 2022 · Proposed COD December 2026

125 MW

Capacity

1

Components

Solar

4y 2m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 11m

Impact Study25%
Queue EntryJan 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

GA

County

Meriwether

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

GTC 115 kV substation on Rocky Mount Rd

Data Source

LBNL

No news available for this project.