Cherry Tree Solar
150 MW hybrid in Washington, GA · In queue since December 2021 · Proposed COD December 2025
150 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
4 years
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
State
GA
County
Washington
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Sandersville-Wadley 230 kV
Data Source
LBNL
This metro Atlanta factory roof is now a solar record-breaker
Beauflor just installed metro Atlanta's largest rooftop solar system, with nearly 2000 panels now powering part of its Georgia factory.
Cherry Street Energy’s unique model to sell solar power to major customers
Michael Chanin knows exactly when the seed of Cherry Street Energy was planted. It was Friday, Sept. 18, 2015.
Cherry Street Energy’s unique model to sell solar power to major customers
Michael Chanin knows exactly when the seed of Cherry Street Energy was planted. It was Friday, Sept. 18, 2015.
Last updated 2026-03-26