SR Rochelle Solar
BetaActiveSolarGTCLBNL
120 MW generation in Wilcox, GA · In queue since December 2021 · Proposed COD November 2026
120 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Construction
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 11m
In Study38%
Queue EntryDec 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-11-01
Project Details
State
GA
County
Wilcox
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Fitzgerald - Pitts 115 kV TL
Data Source
LBNL
No news available for this project.