Talbot Solar
150 MW generation in Talbot, GA · In queue since December 2021 · Proposed COD December 2023
150 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
2 years
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-30
State
GA
County
Talbot
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Talbot County Energy _x0013_ Butler Sub
Data Source
LBNL
Natural gas, renewable options are part of Georgia Power request for more energy
The request includes a mix of natural gas, solar power and battery storage systems that are scheduled to be ready between 2029 and 2031.
Natural gas, renewable options are part of Georgia Power request for more energy
The request includes a mix of natural gas, solar power and battery storage systems that are scheduled to be ready between 2029 and 2031.
Natural gas, renewable options are part of Georgia Power request for more energy
The request includes a mix of natural gas, solar power and battery storage systems that are scheduled to be ready between 2029 and 2031.
Natural gas, renewable options are part of Georgia Power request for more energy
The request includes a mix of natural gas, solar power and battery storage systems that are scheduled to be ready between 2029 and 2031.
Last updated 2026-03-26