SR DeSoto III
BetaActiveSolarBatteryGTCLBNL
60 MW hybrid in Lee, GA · In queue since June 2019 · Proposed COD December 2023
60 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Operational
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 6m
Schedule
27 months past proposed COD
Pre-Study100%
Queue EntryJun 10, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
GA
County
Lee
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
N. Americus - N. Tifton 230 kV TL
Data Source
LBNL
No news available for this project.