Fairboro Solar
BetaActiveSolarGTCLBNL
200 MW generation in Ware, GA · In queue since December 2021 · Proposed COD December 2023
200 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2 years
Schedule
27 months past proposed COD
Facilities Study50%
Queue EntryDec 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-30
Project Details
State
GA
County
Ware
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Wilsonville _x0013_ Kettle Creek
Data Source
LBNL
No news available for this project.