Crossroads Solar
150 MW hybrid in Liberty, GA · In queue since June 2021 · Proposed COD May 2024
150 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-30
State
GA
County
Liberty
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Ludowici - Riceboro 115 kV TL
Data Source
LBNL
Will Ohio make a $98 million mistake?
In Morrow County, Ohio, Open Road Renewables has been trying to develop the Crossroads Solar Grazing Center combining solar power with sheep...
Are faked public comments about to tank an Ohio solar farm?
Dozens of public comments opposing the $98 million Crossroads Solar project appear to be fabricated.
Are faked public comments about to tank an Ohio solar farm?
Dozens of public comments opposing the $98 million Crossroads Solar project appear to be fabricated. Ohio's siting board may block the...
NiSource switches on 200-MW solar site in Indiana
US utility NiSource Inc (NYSE:NI) announced today the commissioning of a 200-MW solar farm in White County, Indiana, representing the third...
Last updated 2026-03-26