Dellwood Solar
BetaActiveSolarBatteryGTCLBNL
150 MW hybrid in Emanuel, GA · In queue since May 2021 · Proposed COD February 2024
150 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 9m
Schedule
25 months past proposed COD
Facilities Study50%
Queue EntryMay 4, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-02-28
Project Details
State
GA
County
Emanuel
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Vidalia-Wadley Primary (white) 230 kV line
Data Source
LBNL