Moxley Solar — Project Summary

Queue ID
GTC-GI-145
Capacity
120 MW
Technology
Solar
Status
active
Location
Jefferson, GA
Region
Southeast
Developer
IA Status
Facility Study

Moxley Solar

BetaActiveSolarGTCLBNL

120 MW generation in Jefferson, GA · In queue since November 2020 · Proposed COD December 2024

120 MW

Capacity

1

Components

Solar

5y 4m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 1m

Schedule

15 months past proposed COD

Facilities Study50%
Queue EntryNov 16, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

GA

County

Jefferson

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Tiger Creek- Wadley Primary 230kV line

Data Source

LBNL