Cherry Blossom Solar
BetaActiveSolarBatteryGTCLBNL
150 MW hybrid in Twiggs, GA · In queue since August 2020 · Proposed COD June 2023
150 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 10m
Schedule
34 months past proposed COD
Facilities Study50%
Queue EntryAug 13, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-15
Project Details
State
GA
County
Twiggs
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Danville 115 kV Substation
Data Source
LBNL