Cherry Blossom Solar — Project Summary

Queue ID
GTC-GI-142
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Twiggs, GA
Region
Southeast
Developer
IA Status
Facility Study

Cherry Blossom Solar

BetaActiveSolarBatteryGTCLBNL

150 MW hybrid in Twiggs, GA · In queue since August 2020 · Proposed COD June 2023

150 MW

Capacity

1

Components

Solar

5y 7m

In Queue

Facility Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 10m

Schedule

34 months past proposed COD

Facilities Study50%
Queue EntryAug 13, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-06-15

Project Details

State

GA

County

Twiggs

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Danville 115 kV Substation

Data Source

LBNL

No news available for this project.