SR Toombs
BetaActiveSolarGTCLBNL
250 MW generation in Toombs, GA · In queue since April 2020 · Proposed COD November 2024
250 MW
Capacity
1
Components
Solar
5y 11m
In Queue
Construction
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 7m
Schedule
16 months past proposed COD
In Study38%
Queue EntryApr 17, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-30
Project Details
State
GA
County
Toombs
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Wadley Primary - Vidalia 230 kV
Data Source
LBNL