SR Robins Solar
BetaActiveSolarGTCLBNL
280 MW generation in Houston, GA · In queue since April 2020 · Proposed COD November 2025
280 MW
Capacity
1
Components
Solar
5y 11m
In Queue
Construction
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 7m
Schedule
4 months past proposed COD
In Study38%
Queue EntryApr 6, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-30
Project Details
State
GA
County
Houston
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Kathleen - Pitts 230 kV line
Data Source
LBNL
No news available for this project.