SR Vidalia
BetaActiveSolarGTCLBNL
250 MW generation in Toombs, GA · In queue since December 2019 · Proposed COD December 2022
250 MW
Capacity
1
Components
Solar
6y 3m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3 years
Schedule
40 months past proposed COD
Facilities Study50%
Queue EntryDec 4, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-15
Project Details
State
GA
County
Toombs
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Statesboro to Vidalia 230 Kv
Data Source
LBNL
No news available for this project.