Thundering Springs
BetaActiveSolarBatteryGTCLBNL
240 MW hybrid in Laurens, GA · In queue since November 2019 · Proposed COD December 2023
240 MW
Capacity
1
Components
Solar
6y 4m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 1m
Schedule
28 months past proposed COD
Facilities Study50%
Queue EntryNov 26, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
GA
County
Laurens
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
No Dublin-Wadley Prim 230 kV TL
Data Source
LBNL
No news available for this project.