SR Metter
80 MW generation in Candler, GA · In queue since October 2019 · Proposed COD November 2025
80 MW
Capacity
1
Components
Solar
6y 5m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
6y 1m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
State
GA
County
Candler
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Statesboro - Vidalia 230 kV TL
Data Source
LBNL
Georgia Power builds four new battery storage facilities. One’s in Bibb County.
Construction is underway at four new battery energy storage system sites located across Georgia, including one in Bibb County, totaling 765 megawatts of power.
Georgia Power builds four new battery storage facilities. One’s in Bibb County.
Construction is underway at four new battery energy storage system sites located across Georgia, including one in Bibb County, totaling 765 megawatts of power.
Georgia Power builds four new battery storage facilities. One’s in Bibb County.
Construction is underway at four new battery energy storage system sites located across Georgia, including one in Bibb County, totaling 765 megawatts of power.
Georgia Power builds four new battery storage facilities. One’s in Bibb County.
Construction is underway at four new battery energy storage system sites located across Georgia, including one in Bibb County, totaling 765 megawatts of power.
Last updated 2026-03-26