All Star Solar
BetaActiveSolarGTCLBNL
95 MW generation in Appling, GA · In queue since October 2019 · Proposed COD December 2023
95 MW
Capacity
1
Components
Solar
6y 5m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 2m
Schedule
27 months past proposed COD
Facilities Study50%
Queue EntryOct 4, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
GA
County
Appling
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Pine Grove 115 kV Substation
Data Source
LBNL