Dawson Solar — Project Summary

Queue ID
GTC-GI-122
Capacity
150 MW
Technology
Solar
Status
active
Location
Terrell, GA
Region
Southeast
Developer
IA Status
Facility Study

Dawson Solar

BetaActiveSolarGTCLBNL

150 MW generation in Terrell, GA · In queue since September 2019 · Proposed COD December 2022

150 MW

Capacity

1

Components

Solar

6y 6m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 3m

Schedule

40 months past proposed COD

Facilities Study50%
Queue EntrySep 2, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

GA

County

Terrell

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Dawson - Greenhouse Rd 115 KV

Data Source

LBNL

No news available for this project.