Dawson Solar
BetaActiveSolarGTCLBNL
150 MW generation in Terrell, GA · In queue since September 2019 · Proposed COD December 2022
150 MW
Capacity
1
Components
Solar
6y 6m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 3m
Schedule
40 months past proposed COD
Facilities Study50%
Queue EntrySep 2, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-01
Project Details
State
GA
County
Terrell
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Dawson - Greenhouse Rd 115 KV
Data Source
LBNL