Limestone Solar — Project Summary

Queue ID
GTC-GI-118
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Macon, GA
Region
Southeast
Developer
IA Status
Facility Study

Limestone Solar

BetaActiveSolarBatteryGTCLBNL

150 MW hybrid in Macon, GA · In queue since May 2019 · Proposed COD December 2021

150 MW

Capacity

1

Components

Solar

6y 10m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 7m

Schedule

52 months past proposed COD

Facilities Study50%
Queue EntryMay 30, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

GA

County

Macon

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

North Americus _x0013_ Perry 115 kV TL

Data Source

LBNL