Oakhurst Solar Farm — Project Summary

Queue ID
GTC-GI-100
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Mitchell, GA
Region
Southeast
Developer
IA Status
Facility Study

Oakhurst Solar Farm

BetaActiveSolarBatteryGTCLBNL

200 MW hybrid in Mitchell, GA · In queue since April 2017 · Proposed COD December 2021

200 MW

Capacity

1

Components

Solar

8y 11m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

4y 8m

Schedule

53 months past proposed COD

Facilities Study50%
Queue EntryApr 19, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-01

Project Details

State

GA

County

Mitchell

Region

Southeast

Developer

Utility

Georgia Transmission

Entity

GTC

Point of Interconnection

Raccoon Creek 230kV Sub

Data Source

LBNL

No news available for this project.