Oakhurst Solar Farm
BetaActiveSolarBatteryGTCLBNL
200 MW hybrid in Mitchell, GA · In queue since April 2017 · Proposed COD December 2021
200 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
4y 8m
Schedule
53 months past proposed COD
Facilities Study50%
Queue EntryApr 19, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-01
Project Details
State
GA
County
Mitchell
Region
Southeast
Developer
—
Utility
Georgia Transmission
Entity
GTC
Point of Interconnection
Raccoon Creek 230kV Sub
Data Source
LBNL