BetaActiveSolarGrantPUDLBNL
200 MW generation in Grant, WA · In queue since July 2022
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Feasibility Study
IA Status
Interconnection Timeline
Total Duration
3y 8m
Feasibility Study13%
Queue EntryJul 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
WA
County
Grant
Region
West
Developer
—
Utility
Grant County Public Utility District
Entity
GrantPUD
Point of Interconnection
Columbia - Rocky Ford 230 kV line
Data Source
LBNL
No news available for this project.