— Project Summary

Queue ID
GrantPUD-5
Capacity
130 MW
Technology
Solar+Battery
Status
active
Location
Grant, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryGrantPUDLBNL

130 MW hybrid in Grant, WA · In queue since July 2020

130 MW

Capacity

1

Components

Solar

5y 8m

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

5y 8m

Construction75%
Queue EntryJul 23, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

WA

County

Grant

Region

West

Developer

Utility

Grant County Public Utility District

Entity

GrantPUD

Point of Interconnection

Columbia - Rocky Ford 230 kV line

Data Source

LBNL

No news available for this project.