BetaActiveSolarBatteryGrantPUDLBNL
130 MW hybrid in Grant, WA · In queue since July 2020
130 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
5y 8m
Construction75%
Queue EntryJul 23, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
WA
County
Grant
Region
West
Developer
—
Utility
Grant County Public Utility District
Entity
GrantPUD
Point of Interconnection
Columbia - Rocky Ford 230 kV line
Data Source
LBNL
No news available for this project.